‘Box structure’ flyover saves £70m and six months for East West Rail
Engineers have saved £70m of taxpayers’ money by using creative new methods to build a railway flyover as part of the East West Rail project.
Network Rail and the East West Rail Alliance are restoring the Oxford-to-Cambridge line by removing and replacing a flyover which crosses the busy West Coast main line at Bletchley – all while keeping trains and passengers moving safely.
The new structure, on the line between Bicester and Bletchley, is being built to last 120 years with minimal future maintenance required.
Instead of replacing the old flyover like-for-like – which would involve closing the West Coast main line below to build five supporting columns in between the tracks – East West Rail project engineers have used modern methods of construction to build a protective ‘box structure.’
It acts very much like a rectangular railway tunnel, removing the need for separate supporting columns and providing a platform for the flyover to sit on.
This means the West Coast main line – which is one of the busiest mixed-use passenger and freight railway routes in Europe – doesn’t have to be closed during the flyover replacement taking place above as the box structure provides a protective, physical barrier.
This keeps both passenger and freight trains safe below and the workforce safe above.
Mark Cuzner, East West Rail Alliance project director, said: “By working smarter we’ve been able to speed-up the project by around six months. At the start of the project, we built a protective wall next to the West Coast main line so we could safely build the box structure during the day when the railway is open, instead of working piecemeal at night-time when the railway is closed.
“Most of the components for both the box structure, and the flyover, arrived pre-built and were simply assembled on site, like a model kit or set of Duplo bricks. The simplicity of construction meant we could safely reduce the workforce onsite by 60%, cut the previously-forecast cost by £70m and get the job done six months quicker than planned.”
Simon Blanchflower CBE, East West Rail Company chief executive officer, said: “The transformation of the iconic Bletchley flyover has really brought the East West Rail project to life and brings communities from Oxford to Cambridge ever closer to a new, sustainable transport link across the region”
Key figures from this innovative construction technique include:
- £70m saved by reducing the need to close the railway
- Modern methods of construction speeds-up project by six months
- 70% of components arrived pre-built and were simply assembled on site
- Simplicity of construction meant onsite workforce could be reduced by 60%
- New flyover will last 120 years (previous one lasted only 60 years)
In the coming months track will start to be laid over the new structure.
It replaces a 1960s-built concrete railway flyover which wasn’t suitable to carry the new East West railway.
The huge demolition project on the old structure took place throughout 2020 and involved some of the UK’s largest cranes.
For more information on the East West Rail project visit: www.networkrail.co.uk/east-west-rail/
More in Public Transport
Oxford Brookes hosts event looking at the future of autonomous transport
The future of transport and the challenges facing the development of smart, connected and autonomous vehicles was discussed at a two-day event at Oxford Brookes University earlier this month.
BRAND THE BUS! JACKPOT INCREASED IN HUGE BONUS FOR GOOD CAUSES
The first prize in Oxford Bus Company’s Brand the Bus! 2023 competition has just got even bigger, thanks to a new partnership.
OXFORD BUS COMPANY SCOOP ACCOLADE AT INDUSTRY AWARDS
The Oxford Bus Company has been recognised for its customer facing technology innovations, in a prestigious national industry award.
From this author
Ingram aiming to ‘turn the tables’ in quest to reclaim BTCC...
Tom Ingram leaves no doubt about his objective for the forthcoming British Touring Car Championship campaign – he wants to reclaim the biggest prize in UK motorsport, which he first lifted 18 months ago. And he is confident he can do just that.
HENLEY FESTIVAL 2024 UNVEILS PIONEERING VISUAL ARTS SHOWCASE
10 – 14 July 2024 | henley-festival.co.uk | #HenleyFestival | @henleyfestival
Henley Festival Presented by Westcoast – the UK’s only boutique black-tie festival – is delighted to reveal this year’s dazzling visual arts programme, featuring one of Britain’s best-selling figurative painters Mark Demsteader, the Doug Moran National Portrait Prize and Archibald People’s Choice Award-winning artist Esther Erlich, and sculptor Holly Bendall, who creates striking bronzes including a Greenpeace-supported permanent public installation that can be experienced in Porthleven.
Blenheim’s CEO opens up on solar
The first B4 Platinum Quarterly held in the stunning Clementines on the South Lawn at Blenheim Palace encapsulated all that is good about a business community coming together to network. One of B4’s most loyal supporters, Blenheim Palace, played host to over 100 business leaders from across Oxfordshire providing fantastic hospitality and enabling brilliant conversations.